Deliverables

Year 1

Del no.

Deliverable name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

D14.1 Set-up of the Proof-of-Concept innovation-funding scheme WP14 14.2 M12 23/04/2018 Achieved Report
D15.1 Evaluation of cleaning process WP15 15.2 M12 28/06/2018 Achieved Report
D17.1 Material characterization WP17 17.2 M12 30/04/2018 Achieved Report

Year 2

Del no.

Deliverable name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

D18.1 Enabling multi-stage Laser Wakefield Acceleration (LWFA) WP18 18.2 M18 29/10/2018 Achieved Report
D7.1 First beam tests for low emittance rings WP7 7.1 M18 29/10/2018 Achieved Report
D14.2 Academia meets industry event 1 WP14 14.3 M24 09/05/2019 Achieved Report
D14.3 Production of material samples of carbon-based composites and metal-diamond composites WP14 14.4 M24 30/10.2018 Achieved Report
D15.2 Evaluation of systems 1 and 2 WP15 15.3 M24 30/04/2019 Achieved Report
D16.1 Electron beam dynamics studies WP16 16.2 M46 Delayed Delay Report
D3.1 Applications of electron beams in the environmental area WP3 3.3 M24 02/04/2019 Achieved Report

Year 3

Del no.

Deliverable name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

D7.2 Final report on injection schemes and injector studies WP7 7.2 M27 03/06/2019 Achieved Report
D6.1 Ranking of performance degrading mechanisms for hadron storage rings and synchrotrons WP6 6.2 M28 23/10/2019 Achieved Report
D14.4 First long length industrial High Temperature Superconductor WP14 14.5 M30 31/10/2019 Achieved Report
D3.2 Evaluation of new technology for electron beam applications WP3 3.2 M30 07/11/2019 Achieved Report
D18.4 Dielectric structure WP18 18.4 M35 31/03/2020 Achieved Report
D4.1 Report on magnetic shielding for high quality superconducting resonators WP4 4.4 M35 06/04/2020 Achieved Report
D15.3 Evaluation of system 3 WP15 15.4 M36 15/06/2020 Achieved Report
D16.2 Manufacturing of electron gun and power modulator completed WP16 16.3 M46 16/03/2021 Achieved Report
D18.3 Exotic lasers and vortex light beams WP18 18.3 M36 26/06/2020 Achieved Report
D2.1 E-learning course WP2 2.4 M36 27/05/2020 Achieved Report
D3.3 Comparison of different accelerator options for 99mTc and therapeutic isotope production WP3 3.5 M36 22/06/2020 Achieved Report
D5.1 Specialized school on Novel Accelerators for young scientists WP5 5.5 M36 05/11/2019 Achieved Report
D6.2 Report on optimal RAMS characteristics for particle accelerators WP6 6.3 M36 20/12/2019 Achieved
Report
D6.3 Summary of novel methods to reduce accelerator impedance WP6 6.4 M36 27/05/2020 Achieved Report
D7.3 Final report on technology for low emittance rings WP7 7.3 M36 28/05/2020 Achieved Report

Year 4

Del no.

Deliverable name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

D2.2 Final report on coordination of communication/outreach activities WP2 2.2 M37 28/07/2020 Achieved Report
D2.3 Final report on coordination of training activities WP2 2.3 M39 30/09/2020 Achieved Report
D4.2 Design of an efficient klystron WP4 4.2 M47 26/03/2021 Achieved Report
D1.1 Final Report on European Strategy WP1 1.3 M48 22/07/2021 Achieved Report
D3.4 Design of a compact 140 MeV electron linear accelerator WP3 3.4 M42 01/12/2020 Achieved Report
D4.3 Report on pulsed magnets WP4 4.5 M43 09/12/2020 Achieved Report
D17.2 Irradiation effect simulations WP17 17.4 M50 29/06/2021 Achieved Access restricted
D6.4 Report on outstanding open questions and prioritized R&D guidelines for ERLs WP6 6.5 M44 14/01/2021 Achieved Report
D18.5 Pushing back the charge frontier WP18 18.5 M54      
D14.5 Real-time Event Distribution Network brought to openly accessible “product grade level” WP14 14.6 M50 20/05/2021 Achieved Report
D15.4 Final report on thin film technology WP15 15.1 M48 21/04/2021 Achieved Report
D16.3 Tests of electron gun at test stand completed WP16 16.4 M53      
D17.3 Irradiation test results WP17 17.3 M54      
D18.2 LWFA inter-stage transport line completed and tested WP18 18.2 M54      
D4.4 Report on the optimization procedure and technical layout of efficient moderator assemblies WP4 4.3 M46 26/03/2021 Achieved Report
D6.5 White list of ranked far-future accelerator options WP6 6.6 M46 12/04/2021 Achieved Report
D7.4 Final report on the Rings with Ultra-Low Emittance network WP7 7.4 M46 04/06/2021 Achieved Report
D8.1 Report on progress in beam diagnostics for hadron LINACs WP8 8.2 M54      
D8.2 Report on advances in beam diagnostics for hadron synchrotrons WP8 8.3 M54      
D8.3 Report on advances in beam diagnostics for 3rd generation light sources WP8 8.4 M54      
D8.4 Report on advances in beam diagnostics for FELs WP8 8.5 M54      
D5.2 Final EuroNNAc and EAAC Report WP5 5.1
5.2
5.3
M46 08/04/2021 Achieved Report
D9.1 Transnational Access to magnet testing facilities WP9 N/A M60
D10.1 Transnational Access to material testing facilities WP10 N/A M60      
D11.1 Transnational Access to electron and proton beam testing facilities WP11 N/A M60      
D12.1 Transnational Access to radio frequency testing facilities WP12 N/A M60      
D13.1 Transnational Access to plasma beam testing facilities WP13 N/A M60